Assessment of studies for the projects in the Waste Water Treatment Plant of Thessaloniki.

The project is part of the Agreement Framework for the provision of Technical Consultant support services for studies & projects of the Strategic & Operational Plan of EYATH SA

Start Date: 16/09/2019. End date 16/09/2025

The subject of the contract is the provision of technical services with a framework agreement specific to projects and studies in the area of business activity of EYATH S.A., as and when required according to the needs of these projects and studies and of EYATH S.A. With these works, it is sought to address the needs of providing technical consultancy services in the fields of economic, architectural, static, electromechanical, hydraulic and chemical technical studies, as well as studies of IT systems, which will be presented during the preparation of studies and the construction of projects that will concern the implementation of the Strategic and Operational Plan (SOP) of EYATH S.A.

To date, it includes 4 separate contracts, each with a variety of projects and subject matter. It may include up to 15 sub-contracts. Indicative projects:

Sub-contract 2

Within the framework of the 3rd partial contract of the framework agreement with EYATH S.A. the Technical Consultant has been assigned the control of the project studies submitted by the Contractor of the five-year operation of the Waste Treatment Plant to EYATH SA for approval. It includes the studies for the projects:

  1. Biogas interconnection and processing projects
  2. Improved sludge dewatering
  3. Commissioning and optimal utilization of cogeneration machines
  4. Ensuring required digestion volume
  5. WWTP’s energy management system
  6. Covering and deodorization of sludge pre-thickening tanks
  7. Evacuation, maintenance and restart of digesters
  8. Restoration and commissioning of Phase A biological stage
  9. Complementary works of the industrial water network
  10. Medium voltage loop improvement works, supply of spare transformers and installation of power management system
  11. Installation and integration of a safety system in the disinfection unit – chlorine gas neutralization system
  12. Improvements to the WWTP entrance units