Study of the renewal of the electromechanical equipment of Mytilene sewage treatment facilities & Update of the study of Mytilene sewage treatment facilities (Phase 2 Projects).

A. E/M equipment renewal study of Mytilini Wastewater Treatment Facilities – Mechanical, Electrical, Electronic studies

The object of the contract is the final study of the renewal of the electromechanical equipment of the sewage treatment plant of Mytilene, which has been designed for 40,000 i.c.

Compilation of tender documents. Project budget €3,895,350.00.

Entry units. Replacement of equipment

Biological treatment units. Equipment replacement

Industrial water disinfection units. System replacement and/or redesign

Sludge treatment units. Provision of maintenance and/or replacement of part of auxiliary sludge treatment works

B. Update of Mytilene Wastewater Treatment Plant Study (Phase 2 Projects – Mechanical, Electrical, Electronic & Hydraulic Project Studies

The object of the contract is the updating of the definitive study of the expansion projects of the sewage treatment plant of Mytilene which has been studied for 60,000 i.c. (Phase B projects)

Compilation of tender documents. Project budget €1,418,000.00.

Πελάτης
Δ.Ε.Υ.Α. ΛΕΣΒΟΥ
Ημ/νία Υλοποίησης
Aug 2020 – Mar 2021