Vacuum sewage network of Nea Plagia , Chalkidiki region

Hydromanagement Ltd completed the design project for wastewater collection and transportation in Nea Plagia, Chalkidiki. The project serves a population equivalent of 8.300.

The study includes the following construction phases:

  • 402 collection chambers – suction valves 3”.
  • Vacuum sewer system consisting of 5.8 km of HDPE SDR11 piping network with monitoring system
  • Vacuum pumping station: building with basement and superstructure – ventilation – deodorization – automation study.

 

The study was conducted for the consortium “THALIS E.S. S.A. – MESOGEOS S.A.”, which was the contractor of the project.

Πελάτης
THALIS E.S. S.A. – MESOGEOS S.A.
Ημ/νία Υλοποίησης
2017
Είδος έργου
Αρχεία